Project Summary Reports

2023

This report highlights significant projects completed or currently underway at our complex from January to December 2023.  It is not all-inclusive of every work order or activity performed but is a summary of accomplishments that have an impact on the common areas and residents of our complex.  Some months may not be listed as they have no such activities to report.

____________________________________________________________

Townhouses Sold to date 2023:  2

Townhouse Highest Selling Price To Date 2023: $711,000

____________________________________________________________

OCTOBER

  • Newsletter Delivered
  • Garage Door Replaced: #6

SEPTEMBER

  • Arborist completed Work on Trees
  • Roofers completed Work on Roofs
  • Catch Basins in Driveways Repaired: #8/48/71
  • Sanitary Sewers Cleaned: Qty 10

JUNE

  • Townhouse Sold – #84
  • The Annual General Meeting was held 21June23 by ZOOM

MAY

  • Balconies were Resurfaced and the new Parapet Wall was Installed – #32/38/89
  • Periodic Information Certificate was Delivered
  • Household Watermain Taps were Replaced – #28/33
  • Light Illuminating Entrance Sign was Repaired 

APRIL

  • Newsletter Delivered
  • Basement Floor Broken Drain Pipe was Replaced – #54

FEBRUARY

  • Townhouse Sold – #42

2022

This report highlights significant projects completed or currently underway at our complex from January to December 2022.  It is not all-inclusive of every work order or activity performed but is a summary of accomplishments that have an impact on the common areas and residents of our complex.  Some months may not be listed as they have no such activities to report.

____________________________________________________________

Townhouses Sold in year 2022: 9

Townhouse Highest Selling Price in year 2022: $999,999.00

____________________________________________________________

~ end of 2022 highlights ~

DECEMBER

  • Townhouse Sold – #75

NOVEMBER

  • Townhouse Sold – #24
  • Arborist on-site to Prune Trees and Remove Dead and Dying Trees
  • Catch Basins in Driveways Repaired
  • Eavestroughs & Downspouts in Complex Cleaned

OCTOBER

  • Periodic Information Certificate (PIC) Delivered
  • Caps Installed On All Fireplace Chimneys – Qty 74.  Part of the New Siding Project.  The top layer(s) of bricks around the chimneys had deteriorated.
  • New Parapet Wall Installed On Balconies #5, 8, 56
  • Electrical Street Wiring Repaired #47 to #60. Entrance light on the west side is still under repair.
  • Newsletter Delivered

SEPTEMBER

  • Townhouses Sold – #22, 74
  • Roofers are on-site to replace shingles and plywood as needed on partial or complete roofs and install one extra vent on each roof to improve air circulation in the attics. Qty 33 units repaired.

AUGUST

  • Townhouses Sold – #10, 11

JULY

  • Household Watermain Taps Replaced – #33, 74
  • Eavestroughs and Downspouts Cleaned for Entire Complex
  • Garage Doors Replaced – Qty 22

JUNE

  • Monday, June 27, 2022 – The Siding Replacement Project Begins
  • Follow the Siding progress by reading issues of “The Siding Project Communicator” that is published on this site.
  • Townhouse Sold – #49

MAY

  • Periodic Information Certificate (PIC) Distributed
  • Balconies Resurfaced – #5, 8, 56
  • Entrance Doors Street Level Replaced – Qty 2
  • Entrance Doors Balcony Replaced – Qty 10
  • Newsletter Delivered
  • Bay Windows Qty 14, and 1 Window at #91 replaced.  Window Project Completed.

MARCH

  • Garage Doors Replaced – #47, 83

FEBRUARY

  • Townhouses Sold – #19, 61

2021

This report highlights significant projects completed or currently underway at our complex from January to December 2021.  It is not all-inclusive of every work order or activity performed but is a summary of accomplishments that have an impact on the common areas and residents of our complex.  Some months may not be listed as they have no such activities to report.

_________________________________________________________

Townhouses Sold in year 2021: 12

Townhouse Highest Selling Price in year 2021: $800,000

_________________________________________________________

~ end of 2021 highlights ~

DECEMBER

  • Catch Basins in Driveways Repaired: #18, 19, 53, 62, 67, 69, 86
  • Street Light Wiring Repaired – #40 to #60
  • Sanitary Sewers Cleaned – One Beside each Block of Townhomes
  • Outdoor Tap Repaired – #91

NOVEMBER

  • Entrance Door Painted – #91
  • Entrance Doors Replaced – #14, 28, 35, 55, 89
  • Trees Removed – #21, 81
  • Tree Trimmed – #4
  • Eavestroughs & Downspouts were Cleaned Throughout the Complex
  • New Sod was Installed on the Playground Area, Around #91, and Bushes were Removed by #91 and #28

OCTOBER

  • Townhouse Sold – #28
  • Newsletter – 2021/2022 Fall & Winter Delivered
  • Basement Waterproofed – #67
  • Eavestroughs & Downspouts Cleaned out – #5, 20, 48, 59
  • Window Replacement Phase 2 Completed – 22 Front, 8 Back

SEPTEMBER

  • Townhouse Sold – #3
  • #91 – General Cleanup of Lawn Area, Tree Vines, and Backyard 

AUGUST

  • Townhouse Sold – #29

JULY

  • Townhouse Sold – #88
  • The PCC122 Annual General Meeting was convened on 7July21, Electronically
  • Chimney Cap Replaced – #45
  • Eavestroughs & Downspouts Cleaned out – #30
  • Roofs – Shingles and/or Plywood Full or Partially Replaced
  • Household Watermain Tap Replaced – #77

JUNE

  • 3 New Trees Planted on Front Lawns – #9, 61-62, 63-64
  • Eavestroughs & Downspouts were Cleaned Throughout the Complex
  • Household Watermain Tap Replaced – #45
  • Window Replacement Phase 1 Completed – 26 Front, 2 Back

MAY

  • Townhouses Sold – #9, 36
  • Balconies Resurfaced – #11, 86
  • Household Watermain Tap Replaced – #58
  • Eavestroughs & Downspouts Cleaned out – #33
  • Playground Equipment Removed – Inspection revealed that the equipment was old and not safe

APRIL

  • Townhouses Sold – #54, 67
  • Newsletter Delivered
  • Eavestroughs/Downspouts cleaned out – #22

MARCH

  • Townhouse Sold – #77

FEBRUARY

  • Townhouses Sold – #72, 82
  • Garage Doors Replaced – #21, 61, 75, 78

JANUARY

  • Townhouse Sold – #68
  • Garage Doors Replaced – #54, 55, 58, 59

 

2020

This report highlights significant projects completed or currently underway at our complex from January to December 2020.  It is not all inclusive of every workorder or activity performed, but is a summary of accomplishments that have an impact on the common areas and residents of our complex.  Some months may not be listed as they have no such activities to report.

_________________________________________________________

Townhouses Sold in year 2020:  7

Townhouse Highest Selling Price in year 2020: $665,000

Number of Board of Director Meetings Convened in 2020: 16

_________________________________________________________

~ end of 2020 highlights ~

The COVID-19 virus issue caused the delay of starting various projects that we had scheduled for the spring.  Contractors, businesses and services were in lockdown.  We enetered the second phase of opening during the last week of June and were able to proceed with select maintenance projects.

DECEMBER

  • Chimney Caps Replaced on 4 Units
  • Painting the Interior of Unit 91 Completed

NOVEMBER

  • Conducted our first Virtual Annual General Meeting, 4Nov20
  • Balcony Resurfacing Completed for #59 & #83, New Parapet Walls Installed
  • Catch Basins Cleaned
  • Chimney Caps Replaced on 10 Units
  • Eavestroughs and Downspouts Cleaned Throughout the Complex
  • Reserve Fund Study Completed
  • Periodic Information Certificate (PIC) Delivered

OCTOBER

  • Townhouses Sold: #42, #58
  • Balcony Resurfacing Started: #83
  • 2020 – 2021 Fall & Winter Newsletter Delivered
  • Walkways Replaced – Qty 27

SEPTEMBER

  • Arborist On Site to Cut and Trim Trees
  • Entrance Doors Replaced: #54/66/74/84
  • Household Watermain Taps/Valves Replaced: #73
  • Roadway and Parking Lines Painted
  • Roadway Signs Redesigned/Replaced
  • Rusted Vent Pipes on Each Roof Painted
  • Speed Bumps Painted
  • Window Replacement – Phase 2: 39 Windows Front & Back

AUGUST

  • Townhouse Sold: #66
  • Basement Waterproofed – #87
  • Reserve Fund Study Started
  • Shingles Replaced on Full or Partial Sections of Roofs – Qty 34 partial

JULY

  • Townhouse Sold: #35
  • Catch Basins Repaired: #16, 17, 50, 51, 56
  • Entrance Door Painted: #67
  • Driveways Resurfaced: Qty 28
  • Household Watermain Taps/Valves Replaced: #37
  • Roadway Sections Paved /Speed Bumps Topped Up

JUNE

  • Eavestroughs and Downspouts Cleaned Throughout the Complex
  • Balcony Resurfaced – #59
  • Window Replacement – Phase 1: #91 – 4 Sets of Windows

MAY

  • Townhouses Sold: #50, #62
  • 2020 Spring & Summer Newsletter Delivered
  • Periodic Information Certificate (PIC) Delivered
  • Household Watermain Taps/Valves Replaced: #89

MARCH

  • Townhouse Sold: #61
  • Basement Water Pipe Leak Repaired: In Bottom of Wall Between #57 & #58

 

2019

This report highlights significant projects completed or currently underway at our complex from January to December 2019.  It is not all inclusive of every workorder or activity performed, but is a summary of accomplishments that have an impact on the common areas and residents of our complex.  Some months may not be listed as they have no such activities to report.

_________________________________________________________

Townhouses Sold in year 2019: 13

Townhouse Highest Selling Price in year 2019: $589,900   

_________________________________________________________

~ end of 2019 highlights ~

NOVEMBER

  • Townhouses Sold: #45/56
  • Balcony Resurface Repair in Progress #59
  • Driveways Resurfaced: #20/21/48/49
  • Eavestroughs Cleaned
  • Household Leaking Watermain Tap Replaced: #71
  • Sewers Cleaned & Inspected

OCTOBER

  • Townhouse Sold: #36
  • Entrance Doors Replaced: #10/25/60
  • Newsletter Delivered
  • Window Replacement Phase 3 completed

SEPTEMBER

  • Townhouses Sold: #20/49
  • Garage Doors Replaced: #29/44/54

AUGUST

  • Townhouse Sold: #31
  • Window Replacement Phase 2 completed
  • Basement waterproofing completed in one unit
  • Entrance doors re-painted to match garage door green colour (Qty 8)

JULY

  • Roofs re-shingled – Qty 20
  • Arborist work on trees completed

JUNE

  • Townhouses Sold: #30/68
  • Window Replacement Phase 1 completed
  • AGM Meeting

MAY

  • Townhouses Sold: #13/89
  • Evestroughs Cleaned
  • Catch Basin Repaired: #79
  • Owner’s Requisition Meeting

APRIL

  • Townhouse Sold: #23
  • Newsletter Delivered
  • Owner’s Requisition Meeting

MARCH

  • Townhouse Sold: #40

JANUARY

  • Townhouse Sold: #29
  • Basement Floor Drain Replaced: #32
  • Household Leaking Watermain Tap Replaced: #27

 

2018

This report highlights significant projects completed or currently underway at our complex from January to December 2018.  It is not all inclusive of every workorder or activity performed, but is a summary of accomplishments that have an impact on the common areas and residents of our complex.  Some months may not be listed as they have no such activities to report.

_________________________________________________________

Townhouses Sold in year 2018: 1

Townhouse Highest Selling Price in year 2018:  Mid $500,000

Garage Doors Replaced: 0  

_________________________________________________________

~ end of 2018 highlights ~

NOVEMBER

  • Newsletter Delivered

OCTOBER

  • Arborist Work Completed
  • Parking Lines Painted
  • Eavestroughs Cleaned

SEPTEMBER

  • Painted the Back of all Townhomes in the Complex
  • Household Leaking Watermain Tap Replaced: #20

AUGUST

  • Catch Basins Repaired: #’s 8/28/38/77
  • Entrance Doors Replaced: #’s 1/2/32/83
  • Street Light Underground Wiring Replaced: from #40 to #44
  • Phase 1 Window Replacement Completed: 31 Front, 2 Back
  • Again this year, the second and third phases of our window replacement program have been cancelled due to budgetary restraints

JULY

  • Balcony Stairs and Railings Replaced – 16 Units

JUNE

  • Townhouse Sold: #72
  • Catch Basins Repaired: #’s 11/85

MAY

  • Catch Basins Repaired: #’s 20/21
  • Newsletter Delivered

APRIL

  • Balcony Resurfaced: #’s 59/89
  • Evestroughs Cleaned
  • Roof Repairs due to Storm Damage: #’s 28/30/31/32

 

2017

This report highlights significant projects completed or currently underway at our complex from January to December 2017.  It is not all inclusive of every workorder or activity performed, but is a summary of accomplishments that have an impact on the common areas and residents of our complex.  Some months may not be listed as they have no such activities to report.

_________________________________________________________

Townhouses Sold in year 2017: 2

Townhouse Highest Selling Price in year 2017: $650,000

Garage Doors Replaced:  10

_________________________________________________________

~ end of 2017 highlights ~

NOVEMBER

  • Balcony drains scoped and pipes replaced (16)

OCTOBER

  • Sidewalk Concrete Restorations (8) #’s 35/54/55/56/57/58/69/85
  • Sanitary and Storm Drains Cleaned
  • Reserve Fund Study Completed (Study performed every three years)

SEPTEMBER

  • Driveway Resurfaced (12) #’s 31/32/33/61/71/72/79/80/81/85/86/87
  • Household Watermain Tap Replaced #43
  • Roadway Paving – #65 to #78

AUGUST

  • Bricks Disintegrated on Units were Replaced (8) #’s 54/55/57/81/82/85/88/90
  • Catch Basins Repaired #’s 44/45/65

JULY

  • Basement Waterproofed #82
  • Household Watermain Tap Replaced #3
  • All Street Lights were Converted to LED

JUNE

  • Townhouse Sold #67
  • Basement Waterproofed #54
  • Electrical – Underground Street Light Wiring Replaced from #65 to #78
  • Household Watermain Tap Replaced #’s 24/56
  • Garage Door Replaced  #27
  • Landscaping Project – Clean-up and Mulch Garden across from #3
  • As reported at our AGM 12June17, the second and third phases of our window replacementprogram are canceled this year due to budgetary restraints.

MAY

  • Townhouse Sold #8
  • Phase 1 Window Replacement Completed – 25 Front, 3 Back
  • Garage Doors Replaced (9) #’s 8/15/16/18/20/22/24/33/37
  • Eaves Troughs Cleaned
  • Newsletter Delivered

APRIL

  • Balcony Resurfaced (2) #’s 14/86
  • Entrance Door Replaced (3) #’s 17/26/63

FEBRUARY

  • Door from Garage into House Replaced #8
  • Household Watermain Tap Replaced #8

JANUARY

  • Basement Floor Drain Replaced #63
  • City Watermain Tap Replaced #1
  • Household Watermain Tap Replaced #’s 62/63